Points to note:
1. Do not start your project without all approvals in hand
2. Bulk purchase of building materials will save you big time, though you will need a 'trusted' foreman to control stock
3. The head fundi shall become closer than a friend during construction. You have to trust that person and change them very early incase of any doubt in their ability
4. Accounting for all supplies will have to be religious, otherwise you may start to believe that someone is stealing, unfounded
5. Labor costs will scare you stiff, but good labor has never been cheap
6. Try to always challenge the thought pattern of your project team. Obviously you will not over-ride the professionals, but learn to question their suggestions based on logic
7. Finishing could actually finish you due to the costs, hence you have to be very hands-on at the stated stage

HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
iris
#202 Posted : Friday, March 30, 2018 8:30:17 PM
Rank: Member


Joined: 9/11/2014
Posts: 228
Location: Nairobi
obiero wrote:
Points to note:
1. Do not start your project without all approvals in hand
2. Bulk purchase of building materials will save you big time, though you will need a 'trusted' foreman to control stock
3. The head fundi shall become closer than a friend during construction. You have to trust that person and change them very early incase of any doubt in their ability
4. Accounting for all supplies will have to be religious, otherwise you may start to believe that someone is stealing, unfounded
5. Labor costs will scare you stiff, but good labor has never been cheap
6. Try to always challenge the thought pattern of your project team. Obviously you will not over-ride the professionals, but learn to question their suggestions based on logic
7. Finishing could actually finish you due to the costs, hence you have to be very hands-on at the stated stage


Very useful tips Obiero. I much prefer this Obiero to the one that attacks my gender whenever he is displeased
obiero
#203 Posted : Friday, March 30, 2018 9:01:22 PM
Rank: Elder


Joined: 6/23/2009
Posts: 13,475
Location: nairobi
iris wrote:
obiero wrote:
Points to note:
1. Do not start your project without all approvals in hand
2. Bulk purchase of building materials will save you big time, though you will need a 'trusted' foreman to control stock
3. The head fundi shall become closer than a friend during construction. You have to trust that person and change them very early incase of any doubt in their ability
4. Accounting for all supplies will have to be religious, otherwise you may start to believe that someone is stealing, unfounded
5. Labor costs will scare you stiff, but good labor has never been cheap
6. Try to always challenge the thought pattern of your project team. Obviously you will not over-ride the professionals, but learn to question their suggestions based on logic
7. Finishing could actually finish you due to the costs, hence you have to be very hands-on at the stated stage


Very useful tips Obiero. I much prefer this Obiero to the one that attacks my gender whenever he is displeased

@iris I don't remember ever attacking you.. Sorry, all the same

HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
sanity
#204 Posted : Monday, April 02, 2018 11:43:57 AM
Rank: Member


Joined: 1/24/2011
Posts: 407
Location: Nairobi,Kenya
obiero wrote:
Finishing up on the ground units.. Wakati wa plaster imefika





@obiero,naomba contacts za huyo welder
Hope is not a strategy
obiero
#205 Posted : Monday, April 02, 2018 12:37:15 PM
Rank: Elder


Joined: 6/23/2009
Posts: 13,475
Location: nairobi
sanity wrote:
obiero wrote:
Finishing up on the ground units.. Wakati wa plaster imefika





@obiero,naomba contacts za huyo welder

Huyo welder ako South Nyanza karibu Kilgoris.. Will his contact be of help? Please confirm before I engage him

HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
Mkimwa
#206 Posted : Tuesday, April 03, 2018 6:54:29 PM
Rank: Member


Joined: 10/26/2008
Posts: 380
Finishes can do you in..

You spend 200K and come out with a gunia of cables and fittings. Or doors that eventually cost 8K, if you add door frame, door, hinges, locks, etc.. yet you were told a panel door costs 3K!

All the best in finishes.
geofreygachie
#207 Posted : Tuesday, April 03, 2018 9:14:43 PM
Rank: Member


Joined: 2/27/2014
Posts: 454
Location: Republic of Enchantment.
sanity wrote:
obiero wrote:
Finishing up on the ground units.. Wakati wa plaster imefika





@obiero,naomba contacts za huyo welder

If you still looking for a welder ,I can refer you to my elder brother based hapa Baba Dogo ,Ruaraka if need fabrication within Nairobi and it's environs.
Divers - can you laugh in scuba gear, or will you drown? I was wondering. - James May.
hardwood
#208 Posted : Tuesday, April 03, 2018 9:29:11 PM
Rank: Elder


Joined: 7/28/2015
Posts: 9,562
Location: Rodi Kopany, Homa Bay
Mkimwa wrote:
Finishes can do you in..

You spend 200K and come out with a gunia of cables and fittings. Or doors that eventually cost 8K, if you add door frame, door, hinges, locks, etc.. yet you were told a panel door costs 3K!

All the best in finishes.


Been there and done/seen it. You budget 3k for a door as per the cost at the hardware but to have a functional door it ends up costing 8k.
obiero
#209 Posted : Wednesday, April 04, 2018 7:12:26 AM
Rank: Elder


Joined: 6/23/2009
Posts: 13,475
Location: nairobi
Mkimwa wrote:
Finishes can do you in..

You spend 200K and come out with a gunia of cables and fittings. Or doors that eventually cost 8K, if you add door frame, door, hinges, locks, etc.. yet you were told a panel door costs 3K!

All the best in finishes.

Thanks @Mkimwa

HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
Speculz
#210 Posted : Wednesday, April 04, 2018 9:38:08 AM
Rank: Member


Joined: 5/6/2011
Posts: 391
Location: Nairobi
geofreygachie wrote:
sanity wrote:
obiero wrote:
Finishing up on the ground units.. Wakati wa plaster imefika





@obiero,naomba contacts za huyo welder

If you still looking for a welder ,I can refer you to my elder brother based hapa Baba Dogo ,Ruaraka if need fabrication within Nairobi and it's environs.


@Geofreygachie, how is your project coming along? Do you have a contact email I can reach you on As I have a few questions? Thanks.
"You can't have everything. Where would you put it?" - Stephen Wright
slykat
#211 Posted : Wednesday, April 04, 2018 9:38:29 AM
Rank: Member


Joined: 2/20/2007
Posts: 359
obiero wrote:
Mkimwa wrote:
Finishes can do you in..

You spend 200K and come out with a gunia of cables and fittings. Or doors that eventually cost 8K, if you add door frame, door, hinges, locks, etc.. yet you were told a panel door costs 3K!

All the best in finishes.

Thanks @Mkimwa



Talking of which I am looking for quotes for doors and windows. Any quality leads?
Pesa Nane
#212 Posted : Wednesday, April 04, 2018 11:23:17 AM
Rank: Elder


Joined: 5/25/2012
Posts: 4,105
Location: 08c
@Obiero, kindly repost those photos of the exterior wall. I liked the dressing.
Pesa Nane plans to be shilingi when he grows up.
obiero
#213 Posted : Wednesday, April 04, 2018 5:13:30 PM
Rank: Elder


Joined: 6/23/2009
Posts: 13,475
Location: nairobi
Pesa Nane wrote:
@Obiero, kindly repost those photos of the exterior wall. I liked the dressing.

@Pesa Nane thanks for the compliment.. Now, I lost my gallery but will aim to take fresh ones on my next site visit

HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
sanity
#214 Posted : Wednesday, April 04, 2018 7:52:28 PM
Rank: Member


Joined: 1/24/2011
Posts: 407
Location: Nairobi,Kenya
obiero wrote:
sanity wrote:
[quote=obiero]Finishing up on the ground units.. Wakati wa plaster imefika

@obiero,naomba contacts za huyo welder

Huyo welder ako South Nyanza karibu Kilgoris.. Will his contact be of help? Please confirm before I engage him


Thanks Obiero,I need on in Nbi
Hope is not a strategy
sanity
#215 Posted : Wednesday, April 04, 2018 7:54:02 PM
Rank: Member


Joined: 1/24/2011
Posts: 407
Location: Nairobi,Kenya
geofreygachie wrote:
sanity wrote:
[quote=obiero]Finishing up on the ground units.. Wakati wa plaster imefika

@obiero,naomba contacts za huyo welder

If you still looking for a welder ,I can refer you to my elder brother based hapa Baba Dogo ,Ruaraka if need fabrication within Nairobi and it's environs.



Oh yes I do need one in Nbi
Hope is not a strategy
obiero
#216 Posted : Friday, April 06, 2018 10:08:23 PM
Rank: Elder


Joined: 6/23/2009
Posts: 13,475
Location: nairobi









HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
obiero
#217 Posted : Friday, April 06, 2018 10:27:30 PM
Rank: Elder


Joined: 6/23/2009
Posts: 13,475
Location: nairobi
The government joins the low end/affordable unit space with KES 1,500,000 houses on sale at Mavoko https://www.businessdail...86838-ow7077z/index.html

HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
Pesa Nane
#218 Posted : Friday, April 06, 2018 10:48:41 PM
Rank: Elder


Joined: 5/25/2012
Posts: 4,105
Location: 08c
Cheers @Obiero. You doing fine.
Pesa Nane plans to be shilingi when he grows up.
obiero
#219 Posted : Friday, April 06, 2018 11:13:37 PM
Rank: Elder


Joined: 6/23/2009
Posts: 13,475
Location: nairobi
Pesa Nane wrote:
Cheers @Obiero. You doing fine.

@pesanane trying is more like it.. almost seeing the end of the tunnel for the initial units.. hopeful that tenants shall be in, within weeks albeit with negligible rental return.. It's a posterity project

HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
obiero
#220 Posted : Friday, April 20, 2018 9:05:17 AM
Rank: Elder


Joined: 6/23/2009
Posts: 13,475
Location: nairobi
Points to note:
1. Do not start your project without all approvals in hand
2. Bulk purchase of building materials will save you big time, though you will need a 'trusted' foreman to control stock
3. The head fundi shall become closer than a friend during construction. You have to trust that person and change them very early incase of any doubt in their ability
4. Accounting for all supplies will have to be religious, otherwise you may start to believe that someone is stealing, unfounded
5. Labor costs will scare you stiff, but good labor has never been cheap. Foreman current rates should average daily at KES 1,500; fundi KES 1,000 and laborers at KES 450
6. Try to always challenge the thought pattern of your project team. Obviously you will not over-ride the professionals, but learn to question their suggestions based on logic
7. Finishing could actually finish you due to the costs, hence you have to be very hands-on at the stated stage
8. Labor cost on tile work should be based on square meters and the current going rate is not more than KES 250/sqm
9. If site doesn't have water or electricity connections, it is important to start chasing for the same as work progresses on site, else you may end up with a ready unit that has no utilities

HF 30,000 ABP 3.49; KQ 414,100 ABP 7.92; MTN 15,750 ABP 6.45
Users browsing this topic
Guest (3)
18 Pages«<910111213>»
Forum Jump  
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.

Copyright © 2024 Wazua.co.ke. All Rights Reserved.