In a statement to local news, KenGen Managing Director Rebecca Miano said that the 168 MW Olkaria V geothermal power project is on track and construction is 40% complete. She gave that update as part of KenGen’s G2G Innovation seminar that brings together 500 KenGen employees and local and international stakeholders to deliberate and discuss innovative ideas. According to KenGen, it is through these seminars that the concept of geothermal spa was conceived. Other concepts that were hatched include the establishment of KenGen Industrial Park, whose development is at advanced stages.
The Sh40 billion (USD 400 million) Olkaria V project is expected to be commissioned by July 1, 2019 producing 168 MW. She said this is part KenGen’s ambitious green energy project aimed at delivering an additional 720 MW to the current 1,631 MW of renewable energy by 2020.