Labor costs for two maisonnetes
Dahatre
#11 Posted : Thursday, December 20, 2012 9:37:40 AM
Rank: Member

Joined: 12/21/2009
Posts: 602
Thanks Pablo: Looove the diverse opinion of Wazuans! Here is what I am thinking of doing, which blends what you suggest and what Ngong and the Captain suggest above: 1. Have the fundi estimate labor costs for the whole project up to plastering. Electrician, plumber and roofer would give me their separate estimates. 2. Chop the project into smaller but complete phases (e.g Koroga/ground floor slab, walling, stairs and first floor slab etc). 3. Have him estimate labor costs for each of these discrete phases separately. I would gauge whether his estimates are reasonable based on the costs Ngong gave me. Each of the phases would have its own payment schedule. If we disagree at any stage, we can part ways after a phase is done. BTW he comes vetted. I have spoken to some of his former clients and they seem happy. I am planning to go see some of his handiwork pretty soon. More alternative thoughts welcome.
Pablo wrote:
The fundi is giving you a very good deal if he is providing all the KYMs and Fundis. Benchmark labour to be between 25% and 33% of the project cost and youll see how this works out. Your payment plan for the amount is equally important. You should always have his money and let like 25% be paid when everything is done and dusted. However even before u talk costs get his recommendations and actually talk to them.
Dahatre
#12 Posted : Thursday, December 20, 2012 9:42:45 AM
Rank: Member

Joined: 12/21/2009
Posts: 602
What if I may ask, are your labor costs?
kamundu wrote:
I would rather do a labour contract. Im currently doing my 300 m2 house and upto roof, labour cost is way below 500k
Foz00
#13 Posted : Thursday, December 20, 2012 10:51:20 AM
Rank: Member

Joined: 1/13/2011
Posts: 297
Location: Nairobi
1. "I am trying to teach myself how these things are done..." if this is your genuine intention,you have to be on site so no need for head fund earning extra. pay him as a normal fundi let him assemble his team. 2. Fundis over quote on Labour contracts, use daily rates as the basis but ensure they know what they have to deliver daily/ duration of tasks/phases. Pablo has a formula of 1 fundi does 120 ft/day ensure that they know this and if it falls short kata pesa! 3. Never get too firendly with fundis on site i have found that erodes their repect for you and affects their performance
Ngong
#14 Posted : Thursday, December 20, 2012 8:58:23 PM
Rank: Veteran

Joined: 11/17/2012
Posts: 1,461
Location: Ngong Forest
Wewe sasa ukitaka vita na hawa watu kata pesa as you say and you will never win with them no matter how kali you are.
Ngong
#15 Posted : Thursday, December 20, 2012 9:21:20 PM
Rank: Veteran

Joined: 11/17/2012
Posts: 1,461
Location: Ngong Forest
I have done several constructions for my self but every time I contract I get alot of unnecessary conflicts. One almost turned tragic. It happened I got a good fundi from my friends site and he told me the best thing is I contract him labour and he will do a good job and there was no doubt about that. So every time I paid him as agreed he will go ahead and pay his crew half amounts and claim I havent given him enough which was a lie. So this saturday I had a sick person who I had to discharge from hospital,the process to longer past 7pm. I had to pay 1000 shs, to be served at Equity bank upper hill so I get all his cash.I met with him as agreed at a point and gave him all the cash. On getting to my compound at around 9 pm night, I found all the other fundis and WWM waiting for me with faces that suggested this is a final game! I asked them what the matter is and quickly said tupe pesa zetu. I asked again which money? The told me niwache upumbavu and I should not waste their time they have some important matter to do. I told them I owe them nothing since I have given cash to the fundi. They said I am a liar since I always give tokens. Luckily I had my sick person with me who told them I have actually given out their cash. They left promising to come back since the fundi had switched his phone off. So they headed to the fundis home some nyumba za mabati about 20 houses or so. When they knocked his door,he just shouted Wezi and his neighbors came out with all kinds of weapons...
Mo
#16 Posted : Saturday, December 22, 2012 12:30:08 AM
Rank: Member

Joined: 9/21/2007
Posts: 326
Dahatre wrote:
Wazuans: I want to construct 2 4-Bedroom maisonettes and act as my own contractor with consultation from an engineer and an architect. I have located an experienced lead fundi but I do not have a good sense of what the labor costs around ngong/kiserian would be. He quoted 500,000 KES to construct upto the point when the maisonettes are roofed (i.e no plaster, no frames, wiring or plumbing of any kind). Is this reasonable? Thanks for your thoughts/comments.
@Dahatre, my submission would be a huge %age of the labour cost is absolutely determined by the model you opt to take e.g if you are naive in matters construction my advise would be to contract the labour in phases i.e how much for foundation? then ground flr walling, shutter, 1st flr walling, roofing etc. it will save you lots of pain. in case you have time and expertise to supervise then contract a foreman to monitor quality of work but be there to ensure work is done (volume)...i tricky piece if you ask me, those fundis can kula jaro even when you are right there!! remember it takes a thief to catch a thief! my estimates from a recent building 290sqm labour cost varies between 30 and 34% of the cost of material for the super structure (foundation to roofing) and about 50% for finishes (plaster, keys, fittings etc)
Speak your truth quietly and clearly; and listen to others, even the dull and the ignorant; they too have their story.
anika66
#17 Posted : Monday, December 24, 2012 5:17:33 PM
Rank: Member

Joined: 2/25/2010
Posts: 158
[/quote] @Dahatre, my submission would be a huge %age of the labour cost is absolutely determined by the model you opt to take e.g if you are naive in matters construction my advise would be to contract the labour in phases i.e how much for foundation? then ground flr walling, shutter, 1st flr walling, roofing etc. it will save you lots of pain. ] I agree with this. I just completed building my mum a house, my very first project. I used a cousin to supervise and he contracted fundis in phases. I am surprised that building is not so expensive. I am all for phased contracts.
Keeping it all in the family
Dahatre
#18 Posted : Sunday, December 30, 2012 2:28:07 PM
Rank: Member

Joined: 12/21/2009
Posts: 602
Thanks all for your thoughts. @foz appreciate the advice especially the one about not getting too friendly with the fundis. I have been known to do that. @Ngong that sounds awful! I have heard worse though, where inexperienced people get employed and get injured in process and the owner becomes liable....scary thought! @Mo and Anika I plan on doing the phased contract model for many reasons including concern over liability in the case of injury.
banker01
#19 Posted : Sunday, January 20, 2013 10:48:03 PM
Rank: New-farer

Joined: 5/1/2012
Posts: 25
i am going through a similar challenge, will you be supplying the tools also like a cement mixer wheel barrows etc or will the fundi?
Ngong
#20 Posted : Sunday, January 27, 2013 8:02:45 PM
Rank: Veteran

Joined: 11/17/2012
Posts: 1,461
Location: Ngong Forest
Yes! all those and more.
3 Pages<123>
Forum Jump  
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.

Copyright © 2026 Wazua.co.ke. All Rights Reserved.