Dahatre wrote:Wazuans:
I want to construct 2 4-Bedroom maisonettes and act as my own contractor with consultation from an engineer and an architect.
I have located an experienced lead fundi but I do not have a good sense of what the labor costs around ngong/kiserian would be.
He quoted 500,000 KES to construct upto the point when the maisonettes are roofed (i.e no plaster, no frames, wiring or plumbing of any kind). Is this reasonable?
Thanks for your thoughts/comments.
@Dahatre,
my submission would be a huge %age of the labour cost is absolutely determined by the model you opt to take e.g if you are naive in matters construction my advise would be to contract the labour in phases i.e how much for foundation? then ground flr walling, shutter, 1st flr walling, roofing etc. it will save you lots of pain.
in case you have time and expertise to supervise then contract a foreman to monitor quality of work but be there to ensure work is done (volume)...i tricky piece if you ask me, those fundis can kula jaro even when you are right there!! remember it takes a thief to catch a thief!
my estimates from a recent building 290sqm labour cost varies between 30 and 34% of the cost of material for the super structure (foundation to roofing) and about 50% for finishes (plaster, keys, fittings etc)