How is the construction going on for both of you?[/quote]
@jaggernaut Mine is progressing well so far. We are joining the trappers and all for the slab. So far spent 1.2M; upto foundation slab 750K, walling 200K and the first floor slab has so far cost 250K.I expect the slab to cost another 250K to make it a total of 500K.
Breakdown upto foundation slab: Design and approvals 100K, Site House 25K, Water connection 35K,Tools (Wheel barrow, spades, mattocks etc)10K, Labour for foundation trenches 25K Hard Kamba moja stones - 5 lorries 75K, Sand 64ton 70K, ballast 40ton 60K, cement 130bags 87K, Y12 n others 80K, Mixer hire twice(foundation strip and slab)35K, Masons+Kym+foreman Labor 2wks 50K, misc 10K. [/quote]
@amicus mind sharing your email address?[/quote]
@Kamundu karue.mwai at gmail.com
I've reached the critical stage of roofing. Walling for first floor was a bit slower than tha of ground floor. Will be updating you on costs. I'm using clay tiles so timber cost was a bit shocking despite shopping over 4 timber yards. So far timber has cost over 150k
The goal is not to be the richest man in the cemetery; Enjoy life while you can.